Does the ZEC end in 2026?
No: what article 29 of Law 19/1994 says
The Canary Islands Special Zone (ZEC) has no end date of its own. Since the 2023 reform (Royal Decree-Law 8/2023), article 29 of Law 19/1994 ties the authorisation of new registrations to the validity of the EU General Block Exemption Regulation, currently Regulation (EU) 651/2014, or of the regulation replacing it. That Regulation currently applies until 31 December 2026; when the European Commission extends or replaces it, the limit moves with it, with no need for any reform in Spain.
Reports that the deadline to register in the ZEC expires on 31 December 2026 are therefore wrong. This is also the view of the Canary Islands Special Zone Consortium. This page explains what article 29 says, what it means for entities already registered and how an application is made today.
Verification date: 04-11-2026
No end date
Of its own: the limit follows the EU block exemption regulation or its successor (art. 29.2 Law 19/1994)
2 months
For the Governing Board to decide; silence means rejection (art. 41.1)
18 months
To apply for registration after authorisation (art. 47.3 of the Regulations)
What article 29 of Law 19/1994 says
Article 29, headed "Validity of the Canary Islands Special Zone", has three paragraphs in the wording given by Royal Decree-Law 8/2023 (in force since 29 December 2023, with effect from 1 January 2024):
- Art. 29.1. ZEC entities may enjoy the tax incentives for the six years immediately following the end of the validity of Commission Regulation (EU) 651/2014 or of the rule replacing it, and that period may be extended if State-aid rules applicable to the Canary Islands so provide, following notice from the European Commission.
- Art. 29.2. The authorisation of registration in the Official Register of ZEC Entities is limited by the date set in article 59 of that Regulation for the end of its validity, or by that of the rule replacing it.
- Art. 29.3. The continuation of the ZEC is in any event subject to the outcome of the periodic reviews of the European Commission.
The law therefore contains no date of its own. It refers to the EU Regulation that declares certain categories of aid compatible with the internal market. Article 59 of that Regulation currently states that it applies until 31 December 2026, and the European Commission has extended or amended it several times; that date comes from its latest extension, made by Regulation (EU) 2023/1315. Each extension or replacement moves the reference in article 29 without any change to Spanish law.
In other words: 31 December 2026 is the current end of application of the EU Regulation, not a deadline for the ZEC.
Sources: Law 19/1994 (BOE, consolidated text) · Royal Decree-Law 8/2023 (BOE) · Royal Decree 1758/2007 (BOE) · Regulation (EU) 651/2014 (EUR-Lex) · Regulation (EU) 2023/1315 (EUR-Lex)
Why 31 December 2026 is not a ZEC deadline
Verification date: 04-11-2026. Checked against the BOE and the Official Journal of the European Union.
- Since the 2023 reform, article 29 of Law 19/1994 sets no end date of its own for the ZEC. It keeps the wording given to it by Royal Decree-Law 8/2023, in force since 29 December 2023, and no later rule published in the Spanish Official Gazette (BOE) has amended it.
- Article 29.2 ties the authorisation of new registrations to the date on which Regulation (EU) 651/2014, the General Block Exemption Regulation, ceases to apply, "or that of the rule replacing it". Article 59 of that Regulation currently states that it applies until 31 December 2026.
- That date is the current end of application of the EU Regulation, not a ZEC deadline. The European Commission has extended or amended Regulation 651/2014 several times and is preparing its review. When it extends the Regulation or adopts one to replace it, the limit in article 29.2 moves with it, with no need for any reform in Spain.
- The continuation of the ZEC is subject to the periodic reviews of the European Commission (art. 29.3). Any change would come from the text the Commission adopts, on the terms that text sets.
This is also the view of the Canary Islands Special Zone Consortium: since the 2023 reform the ZEC has no validity date in Spanish law, only a reference to the EU Regulation, which is reviewed on a regular basis, and the ZEC continues without any further formality.
How to apply today: from application to registration
These are the steps and time limits set by the rules. No timing is guaranteed beyond the statutory periods: the Governing Board's two months can be suspended, and everything else depends on the documents being complete.
1. Application for prior authorisation
Filed with the ZEC Consortium together with the descriptive report on the activity and a deposit or guarantee for the amount of the registration fee (art. 41.1 of Law 19/1994). Among other details, the application must state the registered office, the corporate purpose, the representatives and where they reside, the amount and location of the investment and the jobs to be created (art. 47.2 of the Regulations approved by Royal Decree 1758/2007).
2. Decision of the Governing Board: two months
The Governing Board (Consejo Rector) grants the authorisation expressly, after a favourable report from the Technical Committee, within two months of the Consortium receiving the application. That period can be suspended in the cases provided by law and, if it expires without an express decision, the application is deemed rejected (art. 41.1 of Law 19/1994).
3. Incorporation of the company
The company may be incorporated before the authorisation and still count as newly created, provided the incorporation is limited to the formal steps and there is no economic activity until registration (art. 41 of the Regulations).
4. Registration in the Official Register of ZEC Entities
Once authorised, there are eighteen months to apply for registration, with the tax identification number and the incorporation documents filed with the Commercial Registry (art. 47.3 of the Regulations). Registration is made within ten days of filing those documents, or the applicant is asked to correct any defects (art. 41.2 of the Law and art. 47.4 of the Regulations).
5. Jobs and investment
The minimum jobs must be created within six months of registration and the minimum investment made within the first two years (art. 31.2.d and e of Law 19/1994). Investments made from the filing of the registration application count (art. 43 of the Regulations).
What these time limits mean in practice
The two-month period starts when the Consortium receives the application. It is a maximum: the Governing Board may decide sooner, but the law does not require it to, and any request to complete the file can suspend the period. A complete file from day one is what keeps the procedure within those two months.
Once the authorisation is granted, article 47.3 of the Regulations allows eighteen months to apply for registration. Having the company incorporated and the documents ready makes it possible to apply for registration as soon as the authorisation arrives and to start the period for jobs and investment.
If your entity is already authorised or registered
A registered entity may enjoy the incentives for the six years immediately following the end of the validity of Regulation (EU) 651/2014 or of the rule replacing it (art. 29.1 of Law 19/1994). Because the reference is the EU Regulation or the one replacing it, that six-year period also moves when the Regulation is extended or replaced, and it may be extended if State-aid rules applicable to the Canary Islands so provide.
Throughout that period the requirements of article 31 must still be met: among others, keeping the annual average headcount and holding the assets of the minimum investment for the period in which the regime is enjoyed, or for their useful life if shorter.
If the entity is authorised but not yet registered, article 47.3 of the Regulations allows eighteen months from the authorisation to apply for registration.
The European Commission reviews
Article 29.3 of Law 19/1994 makes the continuation of the ZEC subject to the periodic reviews of the European Commission. The Commission reviews its State-aid rules periodically: it has extended or amended Regulation 651/2014 several times and is preparing its review.
When the Commission extends that Regulation or adopts one to replace it, the reference in article 29 moves with it. Any change to the conditions would come from the text the Commission adopts, and that text will have to be read to see what it provides.
The firm can also look at which other structures in the Canary Islands may suit your project, each with its own requirements.
What to prepare for the application
These are the requirements of article 31.2 of Law 19/1994 and the details the application must contain under the Regulations. Having them ready shortens the time to a complete file.
- Registered office and place of effective management in the Canary Islands (art. 31.2.a of Law 19/1994).
- At least one director resident in the Canary Islands or, for branches, a legal representative (art. 31.2.b).
- A corporate purpose made up of activities listed in the annex to Law 19/1994 (art. 31.2.c).
- Investment plan: €100,000 on Gran Canaria and Tenerife or €50,000 on El Hierro, Fuerteventura, La Gomera, Lanzarote and La Palma, in tangible or intangible fixed assets, within the first two years from registration (art. 31.2.d). Authorisation without that investment is possible if the jobs to be created and the annual average headcount exceed the minimum.
- Employment plan: 5 jobs on Gran Canaria and Tenerife or 3 on the other islands, created within six months of registration and maintained as an annual average headcount (art. 31.2.e). If the same activity was carried on before, that figure applies as net job creation.
- A descriptive report on the activities supporting their solvency, viability, international competitiveness and contribution to the economic and social development of the Canary Islands. Its content is binding on the entity (art. 31.2.f).
- The application details required by art. 47.2 of the Regulations: intended company name, jobs to be created in the first six months and expected average headcount for the first three years and, if the same activity was carried on before under the same or another owner, a statement to that effect with the average headcount for the previous financial year.
- The deposit or guarantee for the amount of the registration fee, filed with the application (art. 41.1 of Law 19/1994).
For the wider picture of the regime, see the ZEC FAQ.
Frequently asked questions about the validity of the ZEC
Does the ZEC end on 31 December 2026?
No. Since the 2023 reform (Royal Decree-Law 8/2023), article 29 of Law 19/1994 sets no end date of its own for the ZEC. It ties the authorisation of new registrations to the validity of Regulation (EU) 651/2014, the General Block Exemption Regulation, or of the regulation replacing it. That Regulation currently applies until 31 December 2026; when the European Commission extends or replaces it, the limit moves with it, with no need for any reform in Spain.
Why have some reports said the deadline to register in the ZEC is 31 December 2026?
Because that is the date currently written in article 59 of Regulation (EU) 651/2014. It is the current end of application of the EU Regulation, not a ZEC deadline: article 29.2 of Law 19/1994 refers to that date or to the date of the rule replacing it, so it moves when the Commission extends or replaces the Regulation. This is also the view of the Canary Islands Special Zone Consortium.
Is there a time limit to apply for registration in the ZEC?
Spanish law sets no date of its own. The limit for authorising registration is the end of validity of the EU block exemption regulation or of the one replacing it (art. 29.2 of Law 19/1994). What the rules do set are the procedural time limits: two months for the Governing Board to decide on the application (art. 41.1) and eighteen months from authorisation to apply for registration (art. 47.3 of the Regulations approved by Royal Decree 1758/2007).
What happens to companies already registered in the ZEC?
They may enjoy the incentives for the six years immediately following the end of the validity of Regulation (EU) 651/2014 or of the rule replacing it, and that period may be extended if State-aid rules applicable to the Canary Islands so provide, following notice from the European Commission (art. 29.1 of Law 19/1994). Because the reference is the EU Regulation or the one replacing it, that six-year period also moves when the Regulation is extended or replaced. The entity must keep meeting the requirements of art. 31, such as the annual average headcount.
What do the European Commission reviews mean for the ZEC?
The continuation of the ZEC is subject to the periodic reviews that the European Commission carries out (art. 29.3 of Law 19/1994). The Commission has extended or amended Regulation 651/2014 several times and is preparing its review. Any change to the conditions would come from the text the Commission adopts, on the terms that text sets.
How long does the Consortium take to decide on an application?
The Governing Board must grant the authorisation expressly within two months of the Consortium receiving the application. That period can be suspended in the cases provided by law and, if it expires without an express decision, the application is deemed rejected (art. 41.1 of Law 19/1994). Silence counts as a refusal, so the file should be complete from the start.
Do I need to incorporate the company before applying?
It is not compulsory. The company may be incorporated beforehand and still count as newly created if the incorporation is limited to the formal steps and there is no economic activity until registration (art. 41 of the Regulations approved by Royal Decree 1758/2007). After authorisation there are eighteen months to apply for registration with the incorporation documents (art. 47.3).
What documents should I have ready?
The descriptive report on the activities (art. 31.2.f of Law 19/1994), the details the application requires (art. 47.2 of the Regulations: registered office, corporate purpose, representatives and where they reside, amount and location of the investment, jobs to be created), the investment and employment plan for the island concerned, and the deposit or guarantee for the registration fee (art. 41.1).
Want to know whether your project fits the ZEC?
Tell us about your case. The firm reviews the request and offers you a date and time to go through the requirements and the procedure. Your first consultation fee is deducted from our fees if you instruct us.